• Brady Dental Center, Amarillo.
  • Staff saying parts of the office either too cold or too warm.
  • The office has duct issues, we suggest zoning.
  • Start unloading equipment and tools needed.
  • Demo all duct to be replaced with new duct and zoning dampers
  • Start pulling new duct into overhead space and adding the dampers
  • Hanging the zone board on a new wall in back room.
  • Connecting another thermostat to help with the zoning of the office.
  • Test zoning dampers, making sure they are working properly and go through the programable thermostat.
  • Clean up.
  • Our installers have many years of experience.
  • Install crew install new unit, wiring electrical and running all plumbing.
  • Run system through a couple of times making sure everything is in working order.
  • Leave job site cleaner than it was.